Wednesday, September 23, 2009
Roofing 90% Complete
We have had two dry and cool days. Mom and I have worked the past two evenings vacuuming up the water on the main and lower levels. In the lower level alone we vacuumed over 200 gallons of water up. Tomorrow, the framers should have the entire roof up and taped. This is a new taping system (offered by 3M) and is getting good reviews in the construction industry.
Next week the plumber and heating contractor start their rough in work. This is scheduled to last thru October. There will not be much to post, unless we start to backfill around the house. Due to the large amount of rain in the past week (over 8 inches), my large topsoil pile was reduced over four feet. It's washed down the hill! We are meeting tomorrow at the job site to discuss what to do.