Monday, August 17, 2009
House Update
Progress on the house has been good. The plumber has installed the drainage pipes in the lower level, the hot/cold water and drainage pipes in the kitchen and powder room, and installed a radon mitigation system under all of the concrete slab areas.
We are still forming walls in part of the house and plan on pouring these at the end of this week. If we have good weather, the garage area, kitchen area, and lower level concrete slabs will be poured on Friday or Monday. We are keeping our fingers crossed for good weather.
Subscribe to:
Post Comments (Atom)
1 comment:
Sweet!
Post a Comment